Continental Tire, Inc., Keystone Constructors, Sumter, SC
Piping design for the curing utility trench headers for Continental’s tire production facility expansion in Sumter, SC. Systems included 17 bar steam, 4 bar steam, cooling water supply, cooling water return, compressed air, nitrogen, vacuum, clean condensate, and dirty condensate feeding seventy-eight (78) curing presses. Model was used for BIM and clash detection by the General Contractor. Construction plans, sections, and isometrics with BOM were generated from the model for each trench set for Keystone’s use.